The Supreme Court of India recently delivered a judgment in the case of Somdatt Builders Vs NHAI (Somdatt Builders-NCC-NEC JV Vs National Highways Authority of India & Ors.), concerning a contractual dispute over the quantity and rate of geogrid material used in a road construction project.
The Court’s decision clarifies the interpretation of clauses related to variations and rate revisions in construction contracts and underscores the importance of respecting arbitral awards.
Background of the Case
The dispute stemmed from a contract awarded by NHAI to Somdatt Builders-NCC-NEC JV for four-laning a section of NH-2 near Kanpur, Uttar Pradesh, under World Bank Loan Assistance.
During the project’s execution, the required quantity of geogrid material exceeded the estimated amount stated in the Bill of Quantities (BOQ). The central issue was whether this increase constituted a “variation” under the contract, specifically Clauses 51 and 52 and whether it warranted a rate revision.
![AI-gen-Up-highway](https://vibrantattorneys.com/wp-content/uploads/2025/01/AI-gen-Up-highway.webp)
The Dispute Resolution Process
The parties initially referred the dispute to a Dispute Review Board (DRB), which comprised technical experts. The DRB concluded that the increased quantity of geogrid was not a variation under Clause 51 and recommended payment at the original BOQ rate. Dissatisfied with the DRB’s decision, NHAI invoked the arbitration clause, and the matter was referred to an Arbitral Tribunal.
![Dispute Resolution Process AI-gen](https://vibrantattorneys.com/wp-content/uploads/2025/01/Dispute-Resolution-Process-AI-gen.webp)
The Arbitral Tribunal, also composed of technical experts, upheld the DRB’s findings and ruled that the increase in geogrid quantity did not attract the provisions of Clause 52, which dealt with rate revisions for variations. NHAI challenged the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, but the Delhi High Court’s Single Judge dismissed the application, upholding the award.
The High Court’s Decision and Appeal in the Supreme Court
NHAI appealed the Single Judge’s decision to a Division Bench of the High Court.
The Division Bench overturned the arbitral award and the Single Judge’s order, ruling that any variation in quantity, whether instructed or not, should lead to renegotiation of rates.
Somdatt Builders-NCC-NEC (JV) then appealed to the Supreme Court.
![DHC new campus](https://vibrantattorneys.com/wp-content/uploads/2025/01/DHC-new-campus.webp)
The Supreme Court’s Judgment in Somdatt Builders Vs NHAI
The Supreme Court meticulously examined the contract clauses, the DRB and Arbitral Tribunal findings, and the High Court’s judgment. The Court held that the High Court erred in interfering with the arbitral award, emphasizing the limited scope of interference under Section 37 of the Arbitration and Conciliation Act, 1996.
The Court analyzed Clauses 51 and 52 and concluded that the increased quantity of geogrid did not constitute a variation as defined in the contract. It reasoned that the increase was merely an adjustment to the estimated quantity and did not involve a change in the form, quality, or quantity of the works as envisaged in Clause 51.
The Court emphasized that the DRB and Arbitral Tribunal, both comprising technical experts, had interpreted the contract clauses plausibly and correctly. It stressed the importance of respecting arbitral awards, especially when they involve interpretations of contractual terms by experts.
Conclusion
The Supreme Court’s judgment in Somdatt Builders Vs NHAI reinforces the principles of judicial restraint in interfering with arbitral awards and provides valuable guidance on interpreting variation clauses in construction contracts.
The decision highlights the importance of upholding the sanctity of the arbitration process and respecting the expertise of technical arbitrators in resolving complex contractual disputes.
Detailed Case Background (Somdatt Builders Vs NHAI)
The case involved a contract dispute between Somdatt Builders-NCC-NEC (JV), a joint venture comprising Somdatt Builders Pvt. Ltd., Nagarjuna Construction Company, and Navayug Engineering Company Limited, and the National Highways Authority of India (NHAI). The contract, awarded in 2002, pertained to the four-laning and strengthening of a 50 km stretch of NH-2 near Kanpur, Uttar Pradesh, under World Bank Loan Assistance. The contract was valued at Rs. 4,961,183,599.00.
A dispute arose concerning Item No. 7.07 of the Bill of Quantities (BOQ), which dealt with reinforced earth structures, specifically the quantity of geogrid material. The dispute centered on the Engineer’s power to revise the BOQ rates in case of increased quantities, which the appellant contested.
The appellant argued that the increased quantity of geogrid was not due to a design change but resulted from an incorrect estimate provided by NHAI in the tender stage. They contended that the BOQ rate should apply to the entire quantity.
The respondent, NHAI, argued that any increase in quantity, whether instructed or not, constituted a variation under Clause 51 of the contract and allowed for rate renegotiation. They claimed that the increased quantity was due to a design change and that the appellant was notified of the rate renegotiation.
The dispute was initially referred to a Dispute Review Board (DRB), which recommended payment at the BOQ rate. NHAI, dissatisfied with the DRB’s decision, invoked arbitration. The Arbitral Tribunal upheld the DRB’s recommendation, leading NHAI to challenge the award in the High Court.
The High Court’s Single Judge upheld the arbitral award, but a Division Bench overturned it, favouring NHAI’s interpretation of the contract. The appellant then appealed to the Supreme Court.
The Supreme Court, after examining the contract clauses (made for construction contracts), the findings of the DRB and Arbitral Tribunal, and the High Court’s judgment, concluded that the increased quantity of geogrid did not constitute a variation under Clause 51. The Court set aside the High Court’s judgment and restored the arbitral award in favour of the appellant.
Detailed Analysis of Legal Precedents in Somdatt Builders Vs NHAI
The Supreme Court’s decision in the Somdatt Builders Vs NHAI case relied on a series of legal precedents to guide its interpretation of the contractual clauses and the scope of judicial intervention in arbitration.
The Court meticulously analyzed these precedents, extracting key principles and applying them to the facts of the case.
1. Limited Grounds for Interference with Arbitral Awards
The Court referred to the case of MMTC Ltd. Vs. Vedanta Ltd. (2019) 4 SCC 163, which established the limited grounds for challenging an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996. This precedent reinforced the idea that courts should not re-examine the merits of a dispute already decided by an arbitral tribunal, except in specific circumstances like violations of public policy or fundamental illegality.
2. Defining the “Public Policy of India”
The Court drew upon the case of Ssangyong Engineer and Construction Company Ltd. (2019) 15 SCC 131 to clarify the meaning of “public policy of India.” This precedent helped define the boundaries of what constitutes a violation of public policy, including actions that contradict fundamental principles of Indian law, disregard court orders, or go against basic notions of justice and morality.
3. Principles for Challenging Arbitral Awards
The Court referred to the case of PSA Sical Terminals Private Ltd. (2023) 15 SCC 781 to reiterate the principles for challenging an arbitral award. This precedent emphasized that an award can be set aside only on specific grounds, such as violation of natural justice, conflict with morality or justice, or patent illegality that goes to the root of the matter.
4. Circumscribed Scope of Interference under Section 37
The Court relied on the case of Reliance Infrastructure Ltd. (2024) 1 SCC 479 to emphasize the limited scope of interference under Section 37 of the Arbitration and Conciliation Act, 1996. This precedent highlighted the narrow jurisdiction of appellate courts in reviewing arbitral awards, especially when they have been upheld under Section 34.
5. Narrower Scope of Appellate Review
The Court referred to the case of M/s Larsen Air Conditioning and Refrigeration Company (2023) INSC 708 to further emphasize the limited scope of appellate review of arbitral awards. This precedent reinforced the idea that appellate courts should exercise restraint and avoid re-examining the merits of a case already decided by an arbitral tribunal.
6. Respecting Arbitral Interpretations of Contracts
The Court drew upon the case of M/s. Hindustan Construction Company Ltd. (2024) 2 SCC 613 to emphasize the importance of respecting the interpretation of contractual terms by arbitrators. This precedent supported the notion that errors in interpretation by an arbitrator are within their jurisdiction and do not automatically warrant judicial intervention.
Arguments of the Appellant in Somdatt Builders Vs NHAI
The appellant, Somdatt Builders-NCC-NEC (JV), presented several key arguments to support their case:
- NHAI Provided Incorrect Geogrid Quantity: The appellant argued that the core issue was the respondent’s (NHAI) provision of an incorrect estimate of the geogrid quantity in the BOQ. This error was discovered when the appellant prepared the design and received approval from the Engineer.
- Increased Quantity Not Due to Design Change: The appellant emphasized that the increased quantity of geogrid was not a result of any design changes or instructions from the Engineer. Instead, it was solely due to the incorrect information provided by the respondent in the tender stage.
- Engineer Initially Approved BOQ Rate: The appellant pointed out that when the increased quantity was identified, the Engineer initially decided that the BOQ rate would apply to the entire quantity. This decision was later contested by NHAI.
- Consistent Findings by DRB and Arbitral Tribunal: The appellant highlighted the consistent findings in their favour by both the DRB and the Arbitral Tribunal, both comprising technical experts. These bodies concluded that the increased quantity was not a variation under Clause 51.1 and recommended payment at the BOQ rate.
- High Court Exceeded Jurisdiction: The appellant argued that the Division Bench of the High Court erred in overturning the concurrent findings of three lower authorities (DRB, Arbitral Tribunal, and Single Judge) while exercising limited jurisdiction under Section 37 of the 1996 Act.
- Interpretation of Clauses 51 and 52: The appellant contended that the High Court’s interpretation of Clauses 51 and 52 was incorrect and rendered certain provisions impossible. They argued that the term “variation” should be understood in the context of the contract, not through dictionary meanings.
- Automatic Increase Should Be Paid at BOQ Rate: The appellant asserted that in cases of automatic quantity increases, the agreed-upon BOQ rate should apply. Any rate revision could only be considered for instructed variations with a 14-day prior notice, which was not provided in this case.
- Reliance on Precedents: The appellant cited several precedents to support their arguments, including a Delhi High Court judgment in NHAI vs. M/s ITD Cementation India Limited and other Supreme Court decisions emphasizing the limited scope of interference under Section 37 of the 1996 Act.
These arguments collectively presented the appellant’s case, emphasizing the error in the initial quantity estimate, the lack of design change, the consistent findings of expert bodies, and the High Court’s overreach in its decision.
Arguments of the Respondent in Somdatt Builders Vs NHAI
The respondent, National Highways Authority of India (NHAI), presented a contrasting set of arguments to defend their position:
- Variation in Quantity Requires Renegotiation: NHAI relied on Clauses 51 and 52 of the contract, asserting that any increase or decrease in quantity, even if not instructed by the Engineer, constitutes a variation. They argued that Clause 52.1 grants the Engineer the power to fix new rates for all variations, regardless of whether they are instructed or uninstructed.
- Significant Increase in Geogrid Quantity: NHAI emphasized that the quantity of geogrid increased by almost 300% due to a change in the RE wall design. This substantial increase triggered the conditions under Clause 52.2, requiring a rate rework.
- Appellant Was Notified of Rate Renegotiation: NHAI contended that the appellant was notified about the rate renegotiation on October 28, 2003, fulfilling the 14-day notice requirement under Clause 52.2 for instructed variations.
- Estimated Quantities Are Not Binding: NHAI argued that the appellant’s claim of negligence and wrong figures in the BOQ was unfounded because Clause 55.1 of the contract explicitly states that the quantities mentioned are only estimates.
- Arbitral Award Is Contrary to Contract: NHAI argued that the arbitral award was perverse and contrary to the only possible interpretation of the contract clauses. They claimed the Arbitral Tribunal had rewritten the contract by ignoring the plain language and the parties’ intentions, overlooking evidence, and making legally impermissible conclusions.
- Reliance on Precedents: NHAI cited several precedents to support their arguments, including Associate Builders Vs. DDA9, Ssangyong Engineer and Construction Company Ltd. Vs. NHAN0, and PSA Sical Terminals Private Ltd. Vs. Board of Trustees of V.O. Chidambranar Port Trust Tuticorin11.
- The ITD Cementation Case Is Not Applicable: NHAI argued that the NHAI Vs. M/s ITD Cementation India Limited case cited by the appellant was not applicable to the present case because it was a Single Bench judgment and did not address the Engineer’s power to fix new rates under Clause 52.
These arguments collectively presented NHAI’s case, emphasizing the construction contracts provisions for rate renegotiation in cases of variations, the significant increase in geogrid quantity, and the alleged flaws in the arbitral award.
The Legal Provisions as examined in Somdatt Builders Vs NHAI
The Supreme Court’s judgment in the Somdatt Builders-NCC-NEC (JV) vs. NHAI case primarily revolved around the interpretation of specific clauses within the contract agreement and relevant provisions of the Arbitration and Conciliation Act, 1996.
Here’s a detailed look at the legal provisions examined:
Contractual Clauses 51, 52 and 55.1 (not discussed here because of no relevance):
Arbitration and Conciliation Act, 1996:
Section 34
Section 34 of the Arbitration and Conciliation Act, 1996, allows parties to apply for the setting aside of an arbitral award.
The Supreme Court emphasized that a court’s role under Section 34 is not to act as an appellate authority over the arbitral tribunal. The court can only intervene in limited situations, such as when the award violates India’s public policy or involves a fundamental illegality.
Even in such instances, the court’s interference should not extend to reviewing the merits of the case. Instead, it should focus on situations where the arbitral tribunal’s findings are deemed arbitrary, capricious, or perverse, or where the award shocks the conscience of the court.
Furthermore, the Supreme Court highlighted that a court, under Section 34, cannot re-evaluate the evidence presented to the arbitral tribunal or substitute its interpretation of the contract for the arbitrator’s interpretation. If the arbitrator’s perspective is reasonable, even if it’s not the only possible interpretation, the court should refrain from interfering.
Section 37
Section 37 of the Arbitration and Conciliation Act, 1996, governs appeals against orders issued under Section 34, which deals with setting aside an arbitral award.
The Supreme Court stressed that the scope of intervention under Section 37 is even narrower than under Section 34. An appellate court, when considering an appeal under Section 37, cannot conduct an independent review of the award’s merits. Its role is limited to determining whether the court that issued the order under Section 34 acted within its jurisdiction.
The Court emphasized that excessive judicial interference in arbitral awards undermines the Arbitration and Conciliation Act, 1996, which aims to provide an efficient alternative dispute resolution mechanism. In this specific case, the Court found that the High Court had exceeded its authority under Section 37 by re-examining the evidence and substituting its interpretation of the contract for the Arbitral Tribunal’s interpretation. The Court maintained that the Arbitral Tribunal’s interpretation was valid and that the High Court’s intervention was unnecessary.
This interpretation of Sections 34 and 37 highlights the Supreme Court’s commitment to upholding the principles of arbitration law and minimizing judicial interference in arbitral awards. The judgment clarifies the boundaries of judicial review in arbitration cases and reinforces the importance of respecting the autonomy of the arbitral process.
This post is based on the Supreme Court of India’s judgment in Somdatt Builders-NCC-NEC (JV) Vs National Highways Authority of India & Ors. (Civil Appeal No. 2058 of 2012).